Piccadilly Line Upgrade: High Voltage Power Programme
Transport for London · Associate Project Manager
- Context
- A multi-site power upgrade on a live London Underground line, delivered by tier one contractors on NEC Option C target cost contracts.
- Outcome
- Scope disputes settled from the works information before they became claims, contractor costs challenged against issued scope, and an evidenced record of lost access to defend the client’s entitlement position.
Read the full case study
- Challenge
- Keep a multi-contractor, multi-site programme on scope and on cost while protecting the client’s position, without damaging working relationships.
- What I did
-
- Managed contract administration with tier one contractors, using the works information to resolve scope and responsibility questions early.
- Assessed compensation event quotations and variations against issued scope, challenging duplicated labour, preliminaries and management cost, and securing contingency items as separately priced options.
- Raised early warnings on access disruption, design delay and contractor underutilisation, and took them to risk reduction meetings with a clear consequence, likelihood and mitigation for each.
- Took ownership of the frustrated access record, reconciling planned possession shifts against site logbooks to evidence lost productive time.
- Tools
- NEC3 / NEC4 ECC Option C · Works information · Early warning and compensation event processes · Excel
- Stakeholders
- Tier one contractors · Programme delivery and commercial teams · Senior leadership